artwork assembly begins

artwork for the maple st. fire station is beginning to take shape.  here are some shots of work-in-progress:

 
first, we tested the stand-offs with a piece of sample material to make sure there were enough washers and bushings to get a solid connection.  all good.



next, i laid out the whole piece, to finalize the color composition.  the frame is made of aluminum, powder-coated to match the fire station exterior.  it is 18' long and 6' wide or so.

 


the ribbons are made of koda xt.  this 3-form product is 40% recycled material and the only architectural polycarbonate material available to use towards LEED MR 4.1 for recycled content.













the artwork will be lit from behind with solar-powered l.e.d strips.


the first few strips are lofted into place.